How to make 100% progress when closing an issue

Added by Ivan Cenov over 13 years ago

Hi,

Is there some automatic way to make an issue 100% done when changing its state to 'Closed'? I do this manually by now but often forget it.

Ivan


Replies (5)

RE: How to make 100% progress when closing an issue - Added by Anonymous over 13 years ago

I use the redmine_x_closed which closes and sets the completion to 100%, all from my checkin message.

RE: How to make 100% progress when closing an issue - Added by Ivan Cenov over 13 years ago

Same with me; When I commit with closing message (par example "fixes #123") the issue is closed and the progress is 100%.

RE: How to make 100% progress when closing an issue - Added by Ivan Cenov over 13 years ago

Felix Schäfer wrote:

You could also use the redmine builtin: RedmineIssueTrackingSetup.

Thank you. It was in front of my eyes but I haven't seen it. I was searching for a checkbox, it was a drop-down listbox...

Ok, I expected both ways for settting percentage to be mixed... but realized that it is somewhat ambiguous.

Ivan

RE: How to make 100% progress when closing an issue - Added by dj jones over 9 years ago

Four years later - and RedmineIssueTrackingSetup is still a great core feature allowing you to set eg 100% for completed tasks, and in fact a default % for all statuses.