Project

General

Profile

Webcal export

Added by John Ross over 10 years ago

Hi

I have several tasks (which are subtasks of another tasks). All have start and end dates in the future and appear in the calendar correctly. When I use webcal feed, however, everything appears in outlook starting with todays date. All the subtasks have a duration of one day and the parent has a duration starting today and ending with the correct end date. I have also imported into Thunderbird/Lightning with the same outcome. Is there something else I need to configure in redmine for this to work as I expect. That is with the calendar in outlook matching the calendar in redmine?