Defect #184

Issue must have due date to turn up in Gantt

Added by Johan Regnell almost 10 years ago. Updated over 9 years ago.

Status:ClosedStart date:
Priority:NormalDue date:
Assignee:-% Done:

0%

Category:Issues
Target version:0.8
Resolution:Fixed Affected version:

Description

Hi there!
Needless to say - using the redmine for real now and enjoy it!

Suggestion:
If an issue has an assigned "Fixed version" (which has a date) - that should be enough to make the issues
turn up in the Gantt. Else there is an extra, unnecessary step to it)

/JR

Associated revisions

Revision 1455
Added by Jean-Philippe Lang over 9 years ago

Gantt chart: display issues that don't have a due date if they are assigned to a version with a date (#184).

History

#1 Updated by Jean-Philippe Lang over 9 years ago

  • Category set to Issues
  • Status changed from New to Closed
  • Target version set to 0.8
  • Resolution set to Fixed

Done in r1455.