Description

Step 1: Create a task
startdate: empty
duedate: 07.01.2015

Step 2: Create a second task
startdate: empty
duedate: 14.01.2015

Step 3: Add a "follows" relation to the second task that links to the first task.
For some reason the second task now has a startdate and the duedate is set to 08.01.2015. Why?

History

#1 Updated by Mischa The Evil almost 3 years ago

  • Status changed from New to Closed
  • Resolution set to Invalid

Please ask questions in the forums.

This is not a defect but a feature, see RedmineIssues#Related-issues.