https://www.redmine.org/https://www.redmine.org/favicon.ico?16793021292012-10-01T23:41:18ZRedmineRedmine - Feature #11999: Calculating issue done ratio based on "Estimated Time" and "Spent Time" - selectable by project (not globally)https://www.redmine.org/issues/11999?journal_id=414122012-10-01T23:41:18ZToshi MARUYAMA
<ul><li><strong>Assignee</strong> deleted (<del><i>Azamat Hackimov</i></del>)</li></ul> Redmine - Feature #11999: Calculating issue done ratio based on "Estimated Time" and "Spent Time" - selectable by project (not globally)https://www.redmine.org/issues/11999?journal_id=435232012-12-18T23:52:42ZGorka Siverio
<ul></ul><p>+10</p>
<p>Besides, we should be able to add another field with the estimated remaining time and use it to calculate a more realistic done ratio. Something like this:</p>
<p>1) Starting:<br />Estimated Time: 8 h<br />Spent Time: 0 h<br />Remaining Time: 8 h<br />% done: 0 %</p>
<p>2) Halfway:<br />Estimated Time: 8 h<br />Spent Time: 4 h<br />Remaining Time: 4 h<br />% done: 50 %</p>
<p>3) Some delay:<br />Estimated Time: 8 h<br />Spent Time: 8 h<br />Remaining Time: 4 h<br />% done: 50 %<br />And since Spent Time + Remaining Time > Estimated Time, we have a delay, and then we should get the red bar to signal it. :D</p>
<p>This way we can get a more reallistic %. What do you think?</p>