https://www.redmine.org/https://www.redmine.org/favicon.ico?16793021292011-05-20T13:59:50ZRedmineRedmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=290842011-05-20T13:59:50ZCassiano Monteiro
<ul></ul><p>+1!</p>
<p>Not sure about the fields "Category", "Start Date" and "End Date", as they may be different from the parent task. But for sure the field "Version" should be inherited, as it´s important to have the same version so the Gantt is displayed correctly.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=292642011-05-27T13:49:42ZScott Cunningham
<ul></ul><p>+1 to inheriting the version.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=340962011-11-24T19:20:54ZMischa The Evil
<ul><li><strong>Subject</strong> changed from <i>when creating a subtask, pre-fill fields Target Version, Category, Start and End Date </i> to <i>When creating a subtask, pre-fill fields Target version, Category & Start- and Due date </i></li></ul> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=340972011-11-24T19:21:53ZMischa The Evil
<ul><li><strong>Subject</strong> changed from <i>When creating a subtask, pre-fill fields Target version, Category & Start- and Due date </i> to <i>When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent values</i></li></ul> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=393242012-06-27T09:25:52ZMathias Kluba
<ul></ul><p>+1</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=474412013-03-25T15:16:05ZDipan Mehta
<ul></ul><p>+1. This is useful. Also, if we combine this with <a class="issue tracker-2 status-5 priority-4 priority-default closed" title="Feature: Easy creation of sub-task through a quick button (Closed)" href="https://www.redmine.org/issues/13561">#13561</a> - it would be very useful and neat.</p>
<p>For example, when you go by New issue you fill up the complete blank form. Where as when you go by 'Add sub-task' all fields come pre-filled.</p>
<p>However, this is not an ultimate solution. Nothing helps when sub-tasks has old information where as parent task is updated. See <a class="issue tracker-2 status-1 priority-4 priority-default" title="Feature: Make sub-task inherit the properties of parent (New)" href="https://www.redmine.org/issues/13585">#13585</a> for more details.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=536992013-12-09T09:09:28ZKetki Vahalia
<ul></ul><p>+1<br />This is very useful. Every sprint we define the high level deliverable as a task, and then add the detailed subtasks assigned to individual engineers. Having this functionality will make subtask creation much more efficient for us.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=537002013-12-09T09:14:30Zjohn pauljohnp2686@gmail.com
<ul></ul><p>+1<br />This is very useful. Every subtask it takes a lot of time to fill the fields</p>
<p>Fields:</p>
<p>Category<br />Target version<br />Customer<br />Sprint<br />Milestone<br />Features<br />External Ref</p>
<p>when adding a new subtask to Redmine, each of said fields is pre-filled with the parent's task values.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=537012013-12-09T09:16:28Zbinnybintoo binnybintoo
<ul></ul><p>+1<br /> This is very very useful for us, when adding a new subtask to Redmine, each of said fields is pre-filled with the parent's task values.</p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=572402014-07-02T06:55:11ZTobias Maier
<ul></ul><p>+1<br />Inheritance of the <strong>target version</strong> is a mandatory feature if You want to manage a project. Otherwise You need a check tool that checks if there are accidentally subtasks that have a different target version than the parent (that is dangerous!).</p>
<p>I recommend that the project settings allow to configure each tracker field if it will be inherited from the parent (if there is a parent).</p>
<p>However, inheritance should only be a default proposal. Of course there are use cases where it makes sense to have different target versions, e.g.:<br />consider three target versions:<br /><pre>
|----target version intermediate----♢0
|----target version release 1---------------------♢1
|----target version release 2----------------------------------♢2
</pre><br />Now consider tasks that are bound to target versions:</p>
<p><strong>Legal</strong><br /><pre>
|----task-----------------------------------------♢1
+----sub task A-------------------♢0
+----sub task B---------------------------------♢1
</pre></p>
<p><strong>Illegal</strong><br /><pre>
|----task-----------------------------------------♢1
+----sub task A-------------------♢0
+----sub task B----------------------------------------------♢2
</pre></p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=575152014-07-14T07:37:33ZEdosoft Factory
<ul></ul><p>You should checkout Subtasks Inherited Fields Plugin at <a class="external" href="https://github.com/edosoft/redmine-inherit-fields-plugin">https://github.com/edosoft/redmine-inherit-fields-plugin</a></p> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=856982018-06-21T07:38:57ZGo MAEDA
<ul><li><strong>Is duplicate of</strong> <i><a class="issue tracker-2 status-5 priority-4 priority-default closed" href="/issues/13810">Feature #13810</a>: Copy Fields From Parent Ticket When Adding a Subtask</i> added</li></ul> Redmine - Feature #6217: When creating a subtask, pre-fill fields Target version, Category & Start- and Due date based on parent valueshttps://www.redmine.org/issues/6217?journal_id=857002018-06-21T07:42:01ZGo MAEDA
<ul><li><strong>Status</strong> changed from <i>New</i> to <i>Closed</i></li></ul><p>The same feature request with <a class="issue tracker-2 status-5 priority-4 priority-default closed" title="Feature: Copy Fields From Parent Ticket When Adding a Subtask (Closed)" href="https://www.redmine.org/issues/13810">#13810</a>.</p>