Copy task with children to a new project.
| Status: | New | Start date: | 2010-09-20 | |
|---|---|---|---|---|
| Priority: | Normal | Due date: | ||
| Assignee: | - | % Done: | 0% |
|
| Category: | Issues | |||
| Target version: | - | |||
| Resolution: |
Description
I have many projects that start with the same set of parent & children tasks:
- Do This Group Of Things
- Setup A
- Configure A
- Test A
- DO That Group Of Things
- Setup B
- Load B
- Compile X
- Test B with X
Often I will select the parent task (Do this Group Of Things) and all of its children and copy it to a new project.
When the tasks appear in the new project the parent/child relationship is gone. All of the tasks are there but there is no subtask assigned to the parent. I have to manually go in and edit each child and attach it to the proper task ID # as the parent.
Related issues
History
#1 Updated by Hans Bangkok about 1 year ago
I don't do this (yet) between Projects, but I found that doing a "Duplicate" of a child task doesn't inherit the Parent field value.