Issue with Gantt chart progress task calculation
Added by Fernnando Dittmar almost 10 years ago
Hello guys,
i'm creating a new project and facing some problems in creating subtasks and get their progress bar calculation right in the Gantt's chart. When i create a parent task(tarefa pai) and later create a subtask for it(tarefa filha) it automatically put 100% progress to the parent task even though my subtask still 0%. Is there something i did wrong?
Thanks in advance!
OBS: FWIW my redmine version is 2.2.3.stable (but tested in the latest version as well).
OBS.: The chart im looking for is exemplified in the figure attached (redmine-gantt).
| redmine-issue2.png (49.6 KB) redmine-issue2.png | creating subtask(tarefa filha) to the parent task(tarefa pai) | ||
| redmine-issue.png (69.2 KB) redmine-issue.png | gantt chart | ||
| redmine-gantt.jpeg (31.5 KB) redmine-gantt.jpeg | Chart goal |