Subtasks don't resepect following/precedes

Added by Moe H over 11 years ago. Updated about 11 years ago.

Status:
Closed
Priority:
Normal
Category:
Issues planning
Target version:
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Fixed
Affected version:

Description

In the current development version, there is a bug
Imagine following scenario:
There are 2 tasks: "Issue1" and "Issue2", and "Issue2" follows "Issue 1" by x days. This works fine. But if I add an subtask to "Issue2" the startdate is not correctly set to Issue1.enddate + x, instead it is possible to set any date you want, without respecting the Issue Relation.

Furthermore, it is possible to set a relation so the subtask precedes "Issue 1", which creates a circular dependency.