Feature #9415

More fine dependencies between issues

Added by Jan BaroŇ° almost 7 years ago. Updated almost 7 years ago.

Status:NewStart date:2011-10-13
Priority:NormalDue date:
Assignee:-% Done:

0%

Category:Issues
Target version:-
Resolution:

Description

Now, only dependecies "precedes" and "follows" exists to order 2 issues time schedule.

I suggest to add more dependencies according project management:
- FS: end A - start B
- SS: start A - start B
- FF: end A - end B
- SF: start A - end B
See eg. http://en.wikipedia.org/wiki/Dependency_(project_management) for a detailed description.

It would allow reschedule of start and due dates of issues base on the dependencies and durations.

Sorry if I submitted a duplicated issue. It is very hard to search in those 2.000+ feature requests.