Defect #29855 » 0002-Make-working_days-consistent-with-add_working_days-w.patch
| app/models/issue.rb | ||
|---|---|---|
| 1414 | 1414 |
(start_date && due_date) ? due_date - start_date : 0 |
| 1415 | 1415 |
end |
| 1416 |
# Returns the duration in working days |
|
| 1416 |
# Returns the duration in working days, counted from the first working day |
|
| 1417 |
# on or after start_date in the same way as #reschedule_on does |
|
| 1417 | 1418 |
def working_duration |
| 1418 |
(start_date && due_date) ? working_days(start_date, due_date) : 0
|
|
| 1419 |
(start_date && due_date) ? working_days(next_working_date(start_date), due_date) : 0
|
|
| 1419 | 1420 |
end |
| 1420 | 1421 |
def soonest_start(reload=false) |
| lib/redmine/utils/date_calculation.rb | ||
|---|---|---|
| 20 | 20 |
module Redmine |
| 21 | 21 |
module Utils |
| 22 | 22 |
module DateCalculation |
| 23 |
# Returns the number of working days between from and to |
|
| 23 |
# Returns the number of working days after from up to and including to, |
|
| 24 |
# so that add_working_days(from, working_days(from, to)) is the last |
|
| 25 |
# working day on or before to |
|
| 26 |
# |
|
| 27 |
# Example: when Saturday and Sunday are non-working days, |
|
| 28 |
# working_days(Sat 2012-10-20, Sun 2012-10-28) returns 5 |
|
| 29 |
# (Mon 2012-10-22 to Fri 2012-10-26), and |
|
| 30 |
# add_working_days(Sat 2012-10-20, 5) returns Fri 2012-10-26 |
|
| 24 | 31 |
def working_days(from, to) |
| 25 | 32 |
days = (to - from).to_i |
| 26 | 33 |
if days > 0 |
| 34 |
# Count by whole weeks first. Any 7 consecutive days contain the |
|
| 35 |
# same number of working days, wherever the weeks start. |
|
| 27 | 36 |
weeks = days / 7 |
| 28 | 37 |
result = weeks * (7 - non_working_week_days.size) |
| 38 |
# Remainder loop: check day by day the remaining days, starting |
|
| 39 |
# from the day after from |
|
| 29 | 40 |
days_left = days - weeks * 7 |
| 30 | 41 |
start_cwday = from.cwday |
| 31 | 42 |
days_left.times do |i| |
| 32 |
unless non_working_week_days.include?(((start_cwday + i - 1) % 7) + 1)
|
|
| 43 |
unless non_working_week_days.include?(((start_cwday + i) % 7) + 1) |
|
| 33 | 44 |
result += 1 |
| 34 | 45 |
end |
| 35 | 46 |
end |
| 36 |
result - non_working_dates_count(from, to)
|
|
| 47 |
result - non_working_dates_count(from + 1, to + 1)
|
|
| 37 | 48 |
else |
| 38 | 49 |
0 |
| 39 | 50 |
end |
| test/unit/issue_test.rb | ||
|---|---|---|
| 2438 | 2438 |
issue.reschedule_on '2012-10-13'.to_date |
| 2439 | 2439 |
assert_equal '2012-10-15'.to_date, issue.start_date |
| 2440 | 2440 |
assert_equal '2012-10-25'.to_date, issue.due_date |
| 2441 | ||
| 2442 |
# Starting on Saturday, from Monday 2012-10-15 to Friday 2012-10-19 |
|
| 2443 |
issue = Issue.new(:start_date => '2012-10-13', :due_date => '2012-10-19') |
|
| 2444 |
issue.reschedule_on '2012-10-22'.to_date |
|
| 2445 |
assert_equal '2012-10-22'.to_date, issue.start_date |
|
| 2446 |
assert_equal '2012-10-26'.to_date, issue.due_date |
|
| 2441 | 2447 |
end |
| 2442 | 2448 |
end |
| test/unit/lib/redmine/utils/date_calculation_test.rb | ||
|---|---|---|
| 35 | 35 |
def test_working_days_with_non_working_week_days |
| 36 | 36 |
with_settings :non_working_week_days => %w(6 7) do |
| 37 |
assert_working_days 14, '2012-10-09', '2012-10-27'
|
|
| 37 |
assert_working_days 13, '2012-10-09', '2012-10-27'
|
|
| 38 | 38 |
assert_working_days 4, '2012-10-09', '2012-10-15' |
| 39 |
assert_working_days 4, '2012-10-09', '2012-10-14'
|
|
| 39 |
assert_working_days 3, '2012-10-09', '2012-10-14'
|
|
| 40 | 40 |
assert_working_days 3, '2012-10-09', '2012-10-12' |
| 41 | 41 |
assert_working_days 8, '2012-10-09', '2012-10-19' |
| 42 | 42 |
assert_working_days 8, '2012-10-11', '2012-10-23' |
| 43 |
assert_working_days 2, '2012-10-14', '2012-10-17' |
|
| 44 |
assert_working_days 11, '2012-10-14', '2012-10-30' |
|
| 43 |
assert_working_days 3, '2012-10-14', '2012-10-17' |
|
| 44 |
assert_working_days 12, '2012-10-14', '2012-10-30' |
|
| 45 |
# From Saturday and Sunday to Friday 2012-10-26 |
|
| 46 |
assert_working_days 5, '2012-10-20', '2012-10-26' |
|
| 47 |
assert_working_days 5, '2012-10-21', '2012-10-26' |
|
| 45 | 48 |
end |
| 46 | 49 |
end |
| ... | ... | |
| 76 | 79 |
# Registered on a non-working week day, should not be counted twice |
| 77 | 80 |
NonWorkingDate.create!(:date => '2012-10-13') |
| 78 | 81 |
with_settings :non_working_week_days => %w(6 7) do |
| 79 |
assert_working_days 13, '2012-10-09', '2012-10-27'
|
|
| 82 |
assert_working_days 12, '2012-10-09', '2012-10-27'
|
|
| 80 | 83 |
assert_working_days 1, '2012-10-09', '2012-10-11' |
| 81 |
assert_working_days 0, '2012-10-10', '2012-10-11'
|
|
| 84 |
assert_working_days 1, '2012-10-10', '2012-10-11'
|
|
| 82 | 85 |
assert_working_days 3, '2012-10-11', '2012-10-16' |
| 83 | 86 |
end |
| 84 | 87 |
end |