Time aggregation in issue tree hierarchy

Added by Pavel Kusch almost 14 years ago

Hello,

Is it possible to create one issue say Story and then other issues - Tasks - under Story so that tasks times - estimated and spent are aggregated on the story level? Any plugin?

Thanks,
Pavel


Replies (5)

RE: Time aggregation in issue tree hierarchy - Added by Pieter Smith almost 14 years ago

As I understand it, time aggregation is standard with sub-tasking (to be released with 1.0). There was a bug where the time would then be doubled in the roadmap (See #5265), but it is solved.

RE: Time aggregation in issue tree hierarchy - Added by Pieter Smith almost 14 years ago

I played with it yesterday evening. Try it out on the demo site (http://demo.redmine.org/) to see if it matches your expectation.

RE: Time aggregation in issue tree hierarchy - Added by Pavel Kusch almost 14 years ago

Looked at it, looks good. So, it will be part of 1.0 release and RC is due in two days. How stable is it? Would you advise to wait a little before using it?

RE: Time aggregation in issue tree hierarchy - Added by Pieter Smith almost 14 years ago

Unfortunately I have not been using Redmine long enough to have passed a few RC's. It generally is a good idea to wait for the first maintenance release. I would still post such a general question in the forums.