%done_ratio task with subtasks 0 estimated
Added by aiv TS about 14 hours ago
Hi, I'm telling you about a problem I'm having...
In my organization, the %done_ratio is very important, and we typically have tasks and subtasks, so the %done_ratio of the parent task depends on the progress of the subtasks. This is typical.
The problem we have is that sometimes there are subtasks whose estimated time is unknown. And we notice that this affects the %done_ratio of the parent task. So, if I don't enter an estimated time in the subtask or I enter a 0 in the estimated time of the task, this causes the behavior of the %done_ratio of the parent task to be different.
So, what would be the recommendation to make the %done_ratio of the parent task automatic and, at the same time, allow it to coexist with subtasks without estimated times without affecting the %done_ratio?
Is there a plugin compatible with versions 5 or 6?
Thank you.