Description

Gantt charts can already be exported into a PDF file.
Could you please add a second export option that creates a graphic file. This file may then be directly inserted in
an Openoffice document.


Files

gantt.png (9.11 KB) gantt.png Philippe Liège, 2008-02-03 11:07
Actions #1

Updated by Jean-Philippe Lang about 19 years ago

Functionality added in r666 (see attached example).

You can now export gantt charts to PNG files if RMagick is available
on your system.