Defect #40348
openParent Task field not available in Import issues screen
0%
Description
Hi,
I'm having troubles when importing issues. I make an import of 5 tasks. Then, I assign those task to several subtasks in a CSV file as Parent Tasks, basically to import all subtasks in this second step.
However, when importing, the field "Parent Task" doesn't appear in the list, so I can't make . Parent TaskField is active in the corresponding tracker. I test it in 2 different instances (4.2.2. and 5.1.2.), and they have the same problem. I can't find a configuration for this, is there someting that I'm missing? Many txs!
(sorry, my instance is in spanish. The field name in spanish for "Parent Task" is "Tarea Padre", and is not there)
Files
Updated by Justin Hemming about 1 month ago
I second this - the How To guide indicates the column header should be "Parent" but this does not appear to be correct?
Updated by Justin Hemming about 1 month ago
Justin Hemming wrote in #note-2:
I also tried Pid as per #50972
Updated by Justin Hemming about 1 month ago
Column header needs to be "Parent Task"