Project

General

Profile

Actions

Feature #2139

closed

Roadmap: use estimated time for calculating progress

Added by Toni Kerschbaum over 15 years ago. Updated over 14 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Roadmap
Target version:
-
Start date:
2008-11-06
Due date:
% Done:

100%

Estimated time:
Resolution:
Fixed

Description

The progress for an item (version) is not calculated correctly.
Currently, the progress seems to be calculated by

number of closed tickets
------------------------- * 100 = progress [%]
number of tickets overall

This is not really correct, since tickets (can) have an estimated time and should be weighted accordingly, e.g.

overall time of closed tickets
------------------------------ * 100 = progress [%]
 overall time of all tickets

Of course, this concludes that every ticket has an estimated time entry.
Therefore estimated time has to be a mandatory field, or tickets without an estimated time would have to be excluded from the calculation.
Nevertheless, I think this is a more correct ansatz for calculating the current progress of a project.


Related issues

Related to Redmine - Feature #2182: Weighted version completion percentageClosed2008-11-13

Actions
Actions

Also available in: Atom PDF