Project

General

Profile

Patch #40798 » 0003-Optimize-Version-behind_schedule-by-avoiding-the-cal.patch

Go MAEDA, 2024-06-13 10:54

View differences:

app/models/version.rb
end
def behind_schedule?
if completed_percent == 100
return false
elsif due_date && start_date
done_date = start_date + ((due_date - start_date+1)* completed_percent/100).floor
return done_date <= User.current.today
else
false # No issues so it's not late
end
# Due date is blank, no issues, or 100% completed, so it's not late
return false if due_date.nil? || start_date.nil? || completed_percent == 100
done_date = start_date + ((due_date - start_date + 1) * completed_percent / 100).floor
done_date <= User.current.today
end
# Returns the completion percentage of this version based on the amount of open/closed issues
(3-3/3)