gantt export to pdf works;but when export to png,chinese character appears ?

Added by gaojun liu over 15 years ago

I don't know why.Exporting to pdf works fine,but when png,chinese character appears ?


Replies (1)

RE: gantt export to pdf works;but when export to png,chinese character appears ? - Added by gaojun liu over 15 years ago

resolved this issue by adding chinese font to redmine