Issue start_date, due_date problem
Added by lee han about 11 years ago
ref attached file.
using:
PostgreSQL
Apache
this problem affect to 'gantt chart' and 'calendar'....
plz solve this problem~
Added more information.
Environment:
Redmine version 2.4.4.stable
Ruby version 2.1.1-p76 (2014-02-24) [x86_64-linux]
Rails version 3.2.17
Environment production
Database adapter PostgreSQL (9.1)
SCM:
Subversion 1.7.14
I downgrade ruby to 2.0.0. but still problem...
Redmine version 2.4.4.stable
Ruby version 2.0.0-p451 (2014-02-24) [x86_64-linux]
Rails version 3.2.17
Environment production
Database adapter PostgreSQL
SCM:
Subversion 1.7.14
date problem.png (37.6 KB) date problem.png |
Replies (1)
RE: Issue start_date, due_date problem
-
Added by Ivan Cenov about 11 years ago
You may create an issue with 'Defect' tracker, attaching the same file there. Also, read Submitting bugs to see what additional information is needed.