How can I get a burndown chart without holiday to show the status of project

Added by shuang guo over 8 years ago

after import Redmine_Agile plugin,we started to use burndown chart.But I found the slope of issue journey contains holiday
We want the slope only reflect the status of working day.
Do I have any method to slove this problem?


Replies (2)

RE: How can I get a burndown chart without holiday to show the status of project - Added by Bernhard Rohloff over 8 years ago

The Agile plugin isn't part of Redmine's core development. I think you should turn over to the guys at RedmineUP who are the creators of the plugin.

RE: How can I get a burndown chart without holiday to show the status of project - Added by Dimitar (RedmineUP) almost 4 years ago

Hi Shuang,

This is Dimitar from the RedmineUP Support Team.

Could you please contact our support team at ? And our support engineers will help you investigate the situation.

We look forward to hearing from you.

Best Regards,
Dimitar from the RedmineUP Support Team

shuang guo wrote:

after import Redmine_Agile plugin,we started to use burndown chart.But I found the slope of issue journey contains holiday
We want the slope only reflect the status of working day.
Do I have any method to slove this problem?