For a given version (says R1), I define a task A with two subtask A.1(2h) and A.2(8h).

When A.1 is done, the progress bar value is 10%
Then if A.2 is done, the progress bar value is 50%

I calculate the issue done ratio with the issue status and done = 100%
It appears that progress computation should not take care of parent estimated time.

Actions #1

Updated by Jean-Philippe Lang almost 12 years ago

  • Subject changed from Progress computation issue to Progress computation issue for versions with subtasks