Remove useless settings when editing a query from the gantt

Defect #16747: Remove useless settings when editing a query from the gantt

Added by Toshi MARUYAMA over 12 years ago. Updated over 12 years ago.

Status:
Closed
Priority:
Normal
Category:
Gantt
Target version:
Resolution:
Fixed
Affected version:

Description

On 2.5.1, gantt sorting is only date.
It is confusing that user can change gantt sorting.

Custom query edit form show gantt options in only gantt custom query edit form,
(hide gantt options in issue list custom query edit form)
so sort option should be hidden in gantt custom query edit form


Files

gantt-hide-custom-query.diff (813 Bytes) gantt-hide-custom-query.diff Toshi MARUYAMA, 2014-04-24 14:22
gantt-custom-query.png (30.3 KB) gantt-custom-query.png Toshi MARUYAMA, 2014-04-24 14:22

Updated by Toshi MARUYAMA over 12 years ago Actions #1

  • Description updated (diff)

Updated by Toshi MARUYAMA over 12 years ago Actions #2

  • Description updated (diff)

Updated by Jean-Philippe Lang over 12 years ago Actions #3

  • Subject changed from Sort option shows in gantt custom query edit form to Remove useless settings when editing a query from the gantt
  • Status changed from New to Resolved
  • Assignee set to Jean-Philippe Lang
  • Resolution set to Fixed

Fixed in r13168, sort options and other settings are removed when editing a query from the gantt chart.

Updated by Jean-Philippe Lang over 12 years ago Actions #4

  • Status changed from Resolved to Closed

Merged.