Mark the Issue closed date on Gantt Chart

Feature #3946: Mark the Issue closed date on Gantt Chart

Added by Aaron Moore about 17 years ago. Updated about 16 years ago.

Status:
New
Priority:
Normal
Assignee:
-
Category:
Gantt
Target version:
-
Resolution:

Description

Display a green (or similar) line indicating the date when an issue was resolved/reached completion. This would show when the actual task was resolved as opposed to when it was scheduled to be completed/resolved.

Case 1:
A user completes issue #1 ahead of schedule and begins working on issue #2. Issue #2 ends up slipping past its deadline and is completed after the due date. By looking at the gantt chart, it should be possible to see when an issue was resolved to better judge the progress of tasks in a project.

Case 2:
There are complaints that User A always holds up the project because he is constantly behind in resolving his issues. By looking at the gantt chart for User A, it would be possible to see his behavior/habit in completing tasks.

Case 3:
By looking at the Gantt chart it should be possible to see if the estimated due date was in line with how long it actually took to implement/resolve some issue. Great for future planning to be able to review an issuers ability to estimate workload and such.


Files

gantt_show_resolved_date.png (39.1 KB) gantt_show_resolved_date.png Aaron Moore, 2009-09-30 02:52

Related issues 1 (1 open — 0 closed)

Related to Redmine - Feature #6795: View issue close date on the gantt viewNewActions

Updated by Mischa The Evil about 16 years ago Actions #1

  • Category set to Gantt

Updated by odile oudre about 16 years ago Actions #2

Can we see different color between over due date, behind schedule