Feature #15886
openCalculation of forecast dates between related tasks
Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:
0%
Estimated time:
Resolution:
Description
- Add field
working hoursin Administration->Settings->Issue tracking

With this field you can calculate the starting date of the next issue related
- Take into account the
Estimated timefield to calculate the date of the next task - Take into account the
Non-working daysfield (Administration->Settings->Issue tracking) to calculate the date of the next task
Files
Updated by Toshi MARUYAMA over 11 years ago
- Tracker changed from Patch to Feature
Updated by @ go2null about 10 years ago
Estimated Time is more of the Effort, rather than the Duration and it is normally used for billing in Redmine.
Also, Redmine code refers to Duration separately.
Some PMP refs:
https://www.passionatepm.com/blog/effort-versus-duration-versus-elapsed-time-pmp-concept-16
http://www.pmbypm.com/difference-project-effort-and-duration/