Description
I have 240 options in my project jump box.
This is annoy when I selected wrong project,
particularly the project located near the bottom of the box.
How about having the project as a default value?
Associated revisions
Sets the current project as the default value of project jump box (#4053).
History
#1
Updated by Jean-Philippe Lang almost 13 years ago
- Category set to UI
- Status changed from New to Closed
- Target version set to 0.8.6
Patch applied in r2959. Thanks.
#2
Updated by Jean-Philippe Lang almost 13 years ago