I can't see how to edit the percentage done field of a task that has subtasks
Added by Dave Sag about 14 years ago
When I have a task with subtasks and I work on that task (not a subtask) it won't let me edit the percentage done field of the task.
See this screen shot showing the Percentage Done popup menu is missing.

Is this a feature or a bug?
| Screen_Shot.png (41 KB) Screen_Shot.png | Screen shot showing missing 'percentage done' menu. |
Replies (5)
RE: I can't see how to edit the percentage done field of a task that has subtasks
-
Added by Mischa The Evil about 14 years ago
Dave Sag wrote:
When I have a task with subtasks and I work on that task (not a subtask) it won't let me edit the percentage done field of the task.
[...]
Is this a feature or a bug?
It's the expected behaviour looking at the way how subtasks are currently implemented within Redmine (see issue #443). When subtasks are available the value of the %-done field is (also) a computation of it's substasks.
RE: I can't see how to edit the percentage done field of a task that has subtasks
-
Added by Cédric HATEM almost 11 years ago
Hello,
I've the same kind of issue.
I can't see and update the "Percentage done field" even for a single and standard task.
Did I made something wrong.
Thanks,
Cédric
RE: I can't see how to edit the percentage done field of a task that has subtasks
-
Added by Cédric HATEM almost 11 years ago
Sorry to disturb. I finaly found...
I was setup in the global setup that % should be calculated as per the status instead of as per user input.
Cédric
RE: I can't see how to edit the percentage done field of a task that has subtasks
-
Added by William Julianto almost 9 years ago
Hello,
May i know how to setup %Done?
if i want to update my project progress everyday,what should i do?
Thanks,
William
RE: I can't see how to edit the percentage done field of a task that has subtasks
-
Added by Nelson TJ over 8 years ago
I too was confused why I couldn't see %Done or Estimated Time. Go to Administration --> Trackers --> make sure you check %Done or whatever standard fields you want for your tracker. That's one of the cool things with Trackers, you can have specific custom fields associated with your tracker.

| percDone.png (10.1 KB) percDone.png |