I can't see how to edit the percentage done field of a task that has subtasks

Added by Dave Sag over 12 years ago

When I have a task with subtasks and I work on that task (not a subtask) it won't let me edit the percentage done field of the task.

See this screen shot showing the Percentage Done popup menu is missing.

Screen shot showing missing 'percentage done' menu.

Is this a feature or a bug?

Screen_Shot.png (41 KB) Screen_Shot.png Screen shot showing missing 'percentage done' menu.

Replies (5)

RE: I can't see how to edit the percentage done field of a task that has subtasks - Added by Mischa The Evil over 12 years ago

Dave Sag wrote:

When I have a task with subtasks and I work on that task (not a subtask) it won't let me edit the percentage done field of the task.

[...]

Is this a feature or a bug?

It's the expected behaviour looking at the way how subtasks are currently implemented within Redmine (see issue #443). When subtasks are available the value of the %-done field is (also) a computation of it's substasks.

RE: I can't see how to edit the percentage done field of a task that has subtasks - Added by Cédric HATEM over 9 years ago

Hello,

I've the same kind of issue.
I can't see and update the "Percentage done field" even for a single and standard task.

Did I made something wrong.

Thanks,

Cédric

RE: I can't see how to edit the percentage done field of a task that has subtasks - Added by Cédric HATEM over 9 years ago

Sorry to disturb. I finaly found...

I was setup in the global setup that % should be calculated as per the status instead of as per user input.

Cédric

RE: I can't see how to edit the percentage done field of a task that has subtasks - Added by William Julianto about 7 years ago

Hello,

May i know how to setup %Done?
if i want to update my project progress everyday,what should i do?

Thanks,
William

RE: I can't see how to edit the percentage done field of a task that has subtasks - Added by Nelson TJ about 7 years ago

I too was confused why I couldn't see %Done or Estimated Time. Go to Administration --> Trackers --> make sure you check %Done or whatever standard fields you want for your tracker. That's one of the cool things with Trackers, you can have specific custom fields associated with your tracker.