Overall gantt diagram showing all projects?

Added by David Brandt over 13 years ago

Hi

I'm quite new to Redmine, and has just got it up running.

I need a plugin that shows all projects i eg. a overall gantt diagram - so I can see when the projects is planned according to each other.

Does anyone know if there is such a plugin for Redmine?


Replies (4)

RE: Overall gantt diagram showing all projects? - Added by Jan Niggemann (redmine.org team member) over 13 years ago

Funny thing, I was looking for the exactly same thing just yesterday... I found nothing notable for 2.2.x...

RE: Overall gantt diagram showing all projects? - Added by David Brandt over 13 years ago

Hi Jan

Actually I found a "hack" to fulfill my needs!
I made a main project, eg "ARCHITECTURAL PROJECTS" and made each of our architectural projects as a sub-projects - see attached screendump!
Would be nice to be able to collapse the sub-projects!

RE: Overall gantt diagram showing all projects? - Added by Mischa The Evil about 13 years ago

David Brandt wrote:

Actually I found a "hack" to fulfill my needs!
I made a main project, eg "ARCHITECTURAL PROJECTS" and made each of our architectural projects as a sub-projects - see attached screendump!

David, you don't need to create such project structure to have a overall gantt chart showing all projects. Such is available in the Redmine core via "top menu left -> Projects -> View all issues -> Issues right sidebar > Gantt". It's routing to http://domain.tld/issues/gantt which is a(n) overall / global / cross-project gantt view.

All the available overall / global / cross-project views are:

View Navigation Route (URL)
overall issue list view "top menu left -> Projects -> View all issues" http://domain.tld/issues
overall calendar view "top menu left -> Projects -> View all issues -> Issues right sidebar > Calendar" http://domain.tld/issues/calendar
overall gantt view "top menu left -> Projects -> View all issues -> Issues right sidebar > Gantt" http://domain.tld/issues/gantt
overall spent time details view "top menu left -> Projects -> Overall spent time [-> Details tab]" http://domain.tld/time_entries
overall spent time report view "top menu left -> Projects -> Overall spent time -> Report tab" http://domain.tld/time_entries/report
overall activity view "top menu left -> Projects -> Overall activity" http://domain.tld/activity
overall news view "top menu left -> Home -> Latest news block left -> View all news", note: Latest news block left is only displayed if at least one news item is created http://domain.tld/news

Would be nice to be able to collapse the sub-projects!

This is not available in the gantt chart (not in the project- nor in the overall gantt). You could open a FR for it if required.

RE: Overall gantt diagram showing all projects? - Added by Ivan Cenov about 13 years ago

When selected all projects the picture is too large (high) and when scrolling left / right one cannot see if a particular project is visible. May be vertical scroll bar should be added.