Cross-year date range in time tracking report misses some hours

Added by Murray Melvin over 11 years ago. Updated about 11 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Time tracking
Target version:
-
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Duplicate
Affected version:

Description

How to reproduce:

  1. Have some tickets that have time tracked in both 2012 and 2013.
  2. Select "last 2 weeks" date preset (or manually enter 2012-12-24 to 2013-01-06)
  3. Select the Report tab
  4. Add Details | Week- Project
  5. Add Details | Week- Issue
  6. Note that the total at the top of the report does not equal the total in the bottom right corner of the report. Times from 2013 have been omitted, although the projects and issues are included.
  7. Also note that the weeks shown in the column headers are 2012-52 and 2012-1

This has also been reported to be a problem in 1.4.4.stable.9879.